Downtown Tunnel closure Schedule, May 26 – June 1

WAVY News

NORFOLK, Va. (WAVY) — This week, drivers traveling between Portsmouth and Norfolk will only have to deal with full-direction closures at the Downtown Tunnel over the weekend.

Here is the latest closure schedule for the I-264 tunnel, from the Elizabeth River Tunnels Project Team.

Eastbound:

  • No full-direction closures from May 26 – June 1
  • Single-lane closures are scheduled for May 26-28 (Tuesday through Thursday), from 8 p.m. each night until 5 a.m. the following morning.

Westbound:

  • Full-direction closures are scheduled for May 29 – June 1, Friday at 8 p.m. until Monday at 5 a.m.
  • No single-lane closures are scheduled for the westbound tube, May 26 – June 1

Due to the nature of construction, closure dates are subject to change.