Duke: Cleanup at Dan River plant will take 2 years

Didi Fung, a contractor for the Environmental Protection Agency, collects water samples from the Dan River as state and federal environmental officials continued their investigations of a spill of coal ash into the Dan River in Eden, N.C., Wednesday, Feb. 5, 2014. Duke Energy estimates that up to 82,000 tons of ash has been released from a break in a 48-inch storm water pipe at the Dan River Power Plant on Sunday. (AP Photo/Gerry Broome)
Didi Fung, a contractor for the Environmental Protection Agency, collects water samples from the Dan River as state and federal environmental officials continued their investigations of a spill of coal ash into the Dan River in Eden, N.C., Wednesday, Feb. 5, 2014. Duke Energy estimates that up to 82,000 tons of ash has been released from a break in a 48-inch storm water pipe at the Dan River Power Plant on Sunday. (AP Photo/Gerry Broome)

RALEIGH, N.C. (AP) — Duke Energy says it plans to move three leaky coal ash pits away from North Carolina waterways, including one that coated 70 miles of the Dan River with toxic sludge.

Duke says it will take at least two years to clean up the Dan River site, and sites near Asheville and Charlotte. State regulators say Duke’s plans fall short of cleaning up nearly three dozen leaky coal ash dumps spread across the state.

After the Feb. 2 spill, Gov. Pat McCrory and regulators gave Duke a March 15 deadline to provide details of how the company would stop pollution at the ash pits.

Duke President Lynn Good sent Department of Environment and Natural Resources Secretary John Skvarla a letter with details.

But on Thursday, Skvarla called the plans inadequate.

 

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.